Posted on: November 22, 2024[ARCHIVED] Bell Road Construction Update

Stage 3 – BELL ROAD PROJECT UPDATE
- Traffic will be shifted onto the Eastern half of Bell Road.
- Construction will take place on the proposed Southbound lanes for Bell Road.
- Meadowview Lane will only be accessible via Southbound Bell Road.
- Homer Junior Highschool will be accessible via Northbound and Southbound Bell Road.
- Generally businesses will be accessible via the respective Northbound and Southbound lanes the same as Stage 2. Northbound/Southbound staged traffic will be divided by concrete barriers so the only crossing of traffic that will occur will be Southbound Bell Road to access Homer Junior Highschool.
- Work to be completed in Stage 3 includes:
- Removal of existing pavement along the west side of Bell Road within the work zone.
- Grading and earthwork for the new road alignment and profile.
- Storm sewer installation.
- Retaining wall and noise barrier wall installation.
- Curb and gutter.
- Binder course/asphalt paving in preparation for Stages 4 and 5.
143rd Street and Bell Road Intersection Project – UTILITY WORK UPDATE
- ComEd has completed a majority of its relocations to the east and west of the 143rd and Bell intersection.
- The next phase of relocation will occur through the intersection itself.
- At this time work in the intersection is anticipated to begin Monday (12/9) or Tuesday (12/10).
- Relocation work is expected to take 1 to 1.5 weeks to complete.
- Traffic patterns will change throughout the duration of the relocation work, please be alert and obey all work zone speed limits and signage!